China's second Hualong-1 brings a good start to the New Year All six units of the Fuqing nuclear power plant are connected to the power grid
2022年01月28日 07:24:52 作者:(Wang Guanghui) 来源: 字号 打印 关闭

Fuzhou Evening NewsAt January 1, 22:35:38, China's independent third-generation nuclear power Hualong brought a good start to the New Year: China National Nuclear Corporation (CNNC) Fuqing Nuclear Power Unit 6 was successfully connected to the grid for the first time and began to send the first degree of electricity to the grid, becoming the world's third and China's second Hualong-1 grid-connected power generation unit, which also means that all six units of Fuqing Nuclear Power have been connected to the grid.

Fuqing Nuclear Power Plant is located in the Qianxue Village, Sanshan Town, Fuqing, and is planned to build six megawatt-class pressurized water reactor nuclear power units, with a total investment of nearly 100 billion RMB. It was planned at a time and constructed continuously; units 1-4 adopt the second generation improved mature nuclear power technology, and units 5-6 are Hualong-1 demonstration projects.

The construction of Fuqing Nuclear Power Unit 6 started on December 22, 2015, and the loading started on November 6, 2021. After the first successful grid connection on the evening of January 1, 2022, it was confirmed on site that all technical indicators met the design requirements and the unit was in good condition, laying a solid foundation for the subsequent official commercial operation.

As the "national business card" of China's nuclear power to the world, Hualong-1 is one of the three-generation nuclear power generation models with the highest acceptance in the current nuclear power market and has been selected as one of the top ten "national facilities" of Chinese central enterprises for two consecutive years. It is the innovative achievement of CNNC in developing and designing the third-generation pressurized water reactor nuclear power with fully independent intellectual property rights based on more than 30 years of experience in nuclear power research, design, construction, operation, and management. At present, Unit 5 of Fuqing Nuclear Power Plant, the world's first Hualong-1 reactor, and Unit 2 of Karachi, Pakistan, the first overseas reactor of Hualong-1, have been put into commercial operation in 2021. 

 

 

 